Agenda Item #49


Title
ACCEPTANCE OF GUARANTEED MAXIMUM PRICE PROPOSAL AND APPROVAL OF CONTRACT FOR CONSTRUCTION FOR PHASE II OF THE SARASOTA MIDDLE SCHOOL-HVAC RENOVATION PROJECT

Description
Under the terms of the 2/1/11 (Item #28) Board approved "Agreement between Owner and Construction Manager for Pre-Construction & Bidding Services", the Director of Construction Services and a member of the Professional Services Selection Committee (PSSC) have successfully negotiated a contract with Jon F. Swift, Inc. for Phase II of the Sarasota Middle School - HVAC Renovation project.  As indicated, the 2/1/11 agreement included pre-construction and bidding services only.  The scope of this contract will include the replacement of the air side HVAC equipment and required electrical upgrades, light fixtures, ceilings, flooring, painting and the remodeling of the existing teacher planning areas into computer assessment labs.  This contract was negotiated on July 14, 2011, and the contract amount is $7,027,105.00.  This contract, which is the standard document utilized for all of the District's construction contracts, is available for review at the Construction Services Department.  The School Board attorney has approved the use of this GMP proposal acceptance form and contract.  Funds for this contract are available in the capital fund.

Recommendation
That the Guaranteed Maximum Price Proposal be accepted as presented and the Contract for Construction for Phase II of the Sarasota Middle School - HVAC Renovation project be approved as presented.

Contact
LEMPE & DOUGHERTY

Financial Impact

CAPITAL: $7,027,105.00